November 21, 2024 (1-month look ahead)

Site Work

  • Mayapple Drive Realignment – Complete
  • Stream Relocation and Detention Areas — Complete

Covered Walkways

  • Complete

Loading Dock Expansion

  • Complete

Town Center Renovation

  • Cabinets and countertops
  • Tile and resilient flooring
  • Accoustical ceilings
  • Painting

Town Center Addition

  • Slab on grade
  • Setting steel

Carriage Homes

  • Spruce – Wall framing
  • Magnolia – Setting steel
  • Aspen – Slab on grade/setting steel

August 2, 2024 Update

Site Utilities

  • Curb/gutter for Mayapple relocation
  • Binder coat of asphalt paving
  • Engineered piers/footings for Carriage Homes
  • Retaining wall and landscaping (east of Mayapple)

Town Center Renovation

  • Rough framing
  • Mechanical (heating, plumbing, electrical)
  • Drywall/taping
  • Acoustical ceiling

Construction Contact

Kevin Swan
Project Development Manager
Email:  kswan01@covliving.org
Phone: 773.878.4507

Emergency Contact

Andrew Suchecki
Director of Facilities Management
Email: asuchecki01@covliving.org
Phone: 847.412.7036  

Post Construction Contact

Michelle Pardun
Executive Director
Email: mpardun@covliving.org
Phone: 847.412.7001

Find us on Facebook